01 <anygantt>
02   <settings>
03     <navigation enabled="True" position="Top" size="30">
04       <buttons collapse_expand_button="true" align="Far" />
05       <text><![CDATA[Activity-Oriented Chart]]></text>
06       <font face="Verdana" size="10" bold="true" color="White" />
07       <background>
08         <fill type="Gradient">
09           <gradient>
10             <key color="#B0B0B0" position="0" />
11             <key color="#A0A0A0" position="0.3" />
12             <key color="#999999" position="0.5" />
13             <key color="#A0A0A0" position="0.7" />
14             <key color="#B0B0B0" position="1" />
15           </gradient>
16         </fill>
17         <border type="Solid" color="#494949" />
18       </background>
19     </navigation>
20     <background enabled="false" />
21   </settings>
22   <timeline>
23     <scale show_start="2000.1.24 0.0" show_end="2000.2.28 0.0">
24       <zoom allow_animation="false" />
25     </scale>
26   </timeline>
27   <project_chart>
28     <tasks>
29       <task id="1" name="Phase 1 - Strategic Plan" parent="" progress="14%" actual_start="2000.1.24 0.0" actual_end="2000.2.28 0.0" />
30       <task id="2" name="Self-Assessment" parent="1" progress="25%" actual_start="2000.1.24 0.0" actual_end="2000.2.2 0.0" />
31       <task id="3" name="Define business vision" parent="2" progress="0%" actual_start="2000.1.24 16.0" actual_end="2000.1.25 1.0" />
32       <task id="4" name="Identify available skills, information and support" parent="2" progress="0%" actual_start="2000.1.25 16.0" actual_end="2000.1.26 1.0" />
33       <task id="5" name="Decide whether to proceed" parent="2" progress="0%" actual_start="2000.1.28 16.0" actual_end="2000.1.29 1.0" />
34       <task id="6" name="Define the Opportunity" parent="1" progress="27%" actual_start="2000.1.29 0.0" actual_end="2000.2.14 0.0" />
35       <task id="7" name="Research the market and competition" parent="6" progress="0%" actual_start="2000.1.29 16.0" actual_end="2000.2.1 1.0" />
36       <task id="8" name="Interview owners of similar businesses" parent="6" progress="60%" actual_start="2000.2.1 0.0" actual_end="2000.2.8 0.0" />
37       <task id="9" name="Identify needed resources" parent="6" progress="0%" actual_start="2000.2.8 16.0" actual_end="2000.2.10 1.0" />
38       <task id="10" name="Identify operating cost elements" parent="6" progress="0%" actual_start="2000.2.10 16.0" actual_end="2000.2.14 1.0" />
39       <task id="11" name="Evaluate Business Approach" parent="1" progress="0%" actual_start="2000.2.14 16.0" actual_end="2000.2.18 1.0" />
40       <task id="12" name="Define new entity requirements" parent="11" progress="0%" actual_start="2000.2.14 16.0" actual_end="2000.2.15 1.0" />
41       <task id="13" name="Identify on-going business purchase opportunities" parent="11" progress="0%" actual_start="2000.2.15 16.0" actual_end="2000.2.16 1.0" />
42       <task id="14" name="Research franchise possibilities" parent="11" progress="0%" actual_start="2000.2.16 16.0" actual_end="2000.2.17 1.0" />
43       <task id="15" name="Summarize business approach" parent="11" progress="0%" actual_start="2000.2.17 16.0" actual_end="2000.2.18 1.0" />
44       <task id="16" name="Evaluate Potential Risks and Rewards" parent="1" progress="0%" actual_start="2000.2.15 16.0" actual_end="2000.2.25 1.0" />
45       <task id="17" name="Assess market size and stability" parent="16" progress="0%" actual_start="2000.2.15 16.0" actual_end="2000.2.17 1.0" />
46       <task id="18" name="Estimate the competition" parent="16" progress="0%" actual_start="2000.2.17 16.0" actual_end="2000.2.18 1.0" />
47       <task id="19" name="Assess needed resource availability" parent="16" progress="0%" actual_start="2000.2.22 16.0" actual_end="2000.2.24 1.0" />
48       <task id="20" name="Evaluate realistic initial market share" parent="16" progress="0%" actual_start="2000.2.24 16.0" actual_end="2000.2.25 1.0" />
49       <task id="21" name="Determine financial requirements" parent="16" progress="0%" actual_start="2000.2.20 16.0" actual_end="2000.2.22 1.0" />
50       <task id="22" name="Review personal suitability" parent="16" progress="0%" actual_start="2000.2.22 16.0" actual_end="2000.2.23 1.0" />
51       <task id="23" name="Evaluate initial profitability" parent="16" progress="0%" actual_start="2000.2.23 16.0" actual_end="2000.2.24 1.0" />
52       <task id="24" name="Review and modify the strategic plan" parent="1" progress="0%" actual_start="2000.2.24 16.0" actual_end="2000.2.28 2.0" />
53       <task id="25" name="Confirm decision to proceed" parent="1" progress="0%" actual_start="2000.2.28 2.0" actual_end1="2000.2.28 2.0" />
54       <task id="26" name="Phase 2 - Define the Business Opportunity" parent="" progress="19%" actual_start="2000.2.28 0.0" actual_end="2000.4.3 0.0" />
55       <task id="27" name="Define the Market" parent="26" progress="28%" actual_start="2000.2.28 0.0" actual_end="2000.3.14 0.0" />
56       <task id="28" name="Access available information" parent="27" progress="0%" actual_start="2000.2.28 17.0" actual_end="2000.2.29 2.0" />
57       <task id="29" name="Create market analysis plan" parent="27" progress="0%" actual_start="2000.2.29 17.0" actual_end="2000.2.31 2.0" />
58       <task id="30" name="Implement market analysis plan" parent="27" progress="40%" actual_start="2000.2.31 0.0" actual_end="2000.3.7 0.0" />
59       <task id="31" name="Identify competition" parent="27" progress="60%" actual_start="2000.3.7 0.0" actual_end="2000.3.11 0.0" />
60       <task id="32" name="Summarize the market" parent="27" progress="0%" actual_start="2000.3.11 17.0" actual_end="2000.3.13 2.0" />
61       <task id="33" name="Identify target market niche" parent="27" progress="0%" actual_start="2000.3.13 17.0" actual_end="2000.3.14 2.0" />
62       <task id="34" name="Identify Needed Materials and Supplies" parent="26" progress="0%" actual_start="2000.3.13 17.0" actual_end="2000.3.22 2.0" />
63       <task id="35" name="Select a business approach (from "Evaluate Business Approach" above)" parent="34" progress="0%" actual_start="2000.3.13 17.0" actual_end="2000.3.15 2.0" />
64       <task id="36" name="Identify management staff resources" parent="34" progress="0%" actual_start="2000.3.17 17.0" actual_end="2000.3.18 2.0" />
65       <task id="37" name="Identify staffing requirements" parent="34" progress="0%" actual_start="2000.3.18 17.0" actual_end="2000.3.19 2.0" />
66       <task id="38" name="Identify needed raw materials" parent="34" progress="0%" actual_start="2000.3.19 17.0" actual_end="2000.3.20 2.0" />
67       <task id="39" name="Identify needed utilities" parent="34" progress="0%" actual_start="2000.3.20 17.0" actual_end="2000.3.21 2.0" />
68       <task id="40" name="Summarize operating expenses and financial projections" parent="34" progress="0%" actual_start="2000.3.21 17.0" actual_end="2000.3.22 2.0" />
69       <task id="41" name="Evaluate Potential Risks and Rewards" parent="26" progress="17%" actual_start="2000.3.24 0.0" actual_end="2000.4.2 0.0" />
70       <task id="42" name="Assess market size and stability" parent="41" progress="50%" actual_start="2000.3.24 0.0" actual_end="2000.3.26 0.0" />
71       <task id="43" name="Assess needed resources availability" parent="41" progress="0%" actual_start="2000.3.26 17.0" actual_end="2000.3.28 2.0" />
72       <task id="44" name="Forecast financial returns" parent="41" progress="0%" actual_start="2000.3.28 17.0" actual_end="2000.4.2 2.0" />
73       <task id="45" name="Review and modify the business opportunity" parent="26" progress="0%" actual_start="2000.4.2 17.0" actual_end="2000.4.3 2.0" />
74       <task id="46" name="Confirm decision to proceed" parent="26" progress="0%" actual_start="2000.4.3 2.0" actual_end="2000.4.3 2.0" />
75       <task id="47" name="Phase 3 - Plan for Action" parent="" progress="17%" actual_start="2000.4.3 0.0" actual_end="2000.5.1 0.0" />
76       <task id="48" name="Develop Detailed 5-Year Business Plan" parent="47" progress="17%" actual_start="2000.4.3 0.0" actual_end="2000.5.1 0.0" />
77       <task id="49" name="Describe the vision and opportunity" parent="48" progress="0%" actual_start="2000.4.3 17.0" actual_end="2000.4.4 2.0" />
78       <task id="50" name="List assumptions" parent="48" progress="0%" actual_start="2000.4.4 17.0" actual_end="2000.4.5 2.0" />
79       <task id="51" name="Describe the market" parent="48" progress="0%" actual_start="2000.4.5 17.0" actual_end="2000.4.6 2.0" />
80       <task id="52" name="Describe the new business" parent="48" progress="0%" actual_start="2000.4.8 17.0" actual_end="2000.4.9 2.0" />
81       <task id="53" name="Describe strengths, weaknesses, assets and threats" parent="48" progress="0%" actual_start="2000.4.9 17.0" actual_end="2000.4.10 2.0" />
82       <task id="54" name="Estimate sales volume during startup period" parent="48" progress="0%" actual_start="2000.4.10 17.0" actual_end="2000.4.11 2.0" />
83       <task id="55" name="Forecast operating costs" parent="48" progress="0%" actual_start="2000.4.11 17.0" actual_end="2000.4.12 2.0" />
84       <task id="56" name="Establish pricing strategy" parent="48" progress="0%" actual_start="2000.4.12 17.0" actual_end="2000.4.13 2.0" />
85       <task id="57" name="Forecast revenue" parent="48" progress="0%" actual_start="2000.4.15 17.0" actual_end="2000.4.16 2.0" />
86       <task id="58" name="X" parent="48" progress="0%" actual_start="2000.4.16 17.0" actual_end="2000.4.18 2.0" />
87       <task id="59" name="Develop break-even analysis" parent="48" progress="0%" actual_start="2000.4.18 17.0" actual_end="2000.4.19 2.0" />
88       <task id="60" name="Develop cash-flow projection" parent="48" progress="0%" actual_start="2000.4.19 17.0" actual_end="2000.4.20 2.0" />
89       <task id="61" name="Identify licensing and permitting requirements" parent="48" progress="0%" actual_start="2000.4.22 17.0" actual_end="2000.4.23 2.0" />
90       <task id="62" name="Develop startup plan" parent="48" progress="100%" actual_start="2000.4.23 17.0" actual_end="2000.4.25 2.0" />
91       <task id="63" name="Develop sales and marketing strategy" parent="48" progress="0%" actual_start="2000.4.25 17.0" actual_end="2000.4.26 2.0" />
92       <task id="64" name="Develop distribution structure" parent="48" progress="0%" actual_start="2000.4.26 17.0" actual_end="2000.4.27 2.0" />
93       <task id="65" name="Describe risks and opportunities" parent="48" progress="20%" actual_start="2000.4.29 0.0" actual_end="2000.4.31 0.0" />
94       <task id="66" name="Publish the business plan" parent="48" progress="0%" actual_start="2000.4.31 17.0" actual_end="2000.5.1 2.0" />
95       <task id="67" name="Confirm decision to proceed" parent="48" progress="0%" actual_start="2000.5.1 2.0" actual_end="2000.5.1 2.0" />
96       <task id="68" name="Phase 4 - Proceed With Startup Plan" parent="" progress="24%" actual_start="2000.5.1 0.0" actual_end="2000.7.24 0.0" />
97       <task id="69" name="Choose a location" parent="68" progress="36%" actual_start="2000.5.1 0.0" actual_end="2000.5.2 0.0" />
98       <task id="70" name="Establish Business Structure" parent="68" progress="14%" actual_start="2000.5.2 0.0" actual_end="2000.6.11 0.0" />
99       <task id="71" name="Choose a Name" parent="70" progress="33%" actual_start="2000.5.2 0.0" actual_end="2000.5.6 0.0" />
100       <task id="72" name="Identify implications" parent="71" progress="40%" actual_start="2000.5.2 0.0" actual_end="2000.5.3 0.0" />
101       <task id="73" name="Research name availability" parent="71" progress="0%" actual_start="2000.5.5 17.0" actual_end="2000.5.6 2.0" />
102       <task id="74" name="Choose a Bank" parent="70" progress="0%" actual_start="2000.5.6 17.0" actual_end="2000.5.13 2.0" />
103       <task id="75" name="Establish accounts" parent="74" progress="0%" actual_start="2000.5.6 17.0" actual_end="2000.5.10 2.0" />
104       <task id="76" name="Establish line of credit" parent="74" progress="0%" actual_start="2000.5.12 17.0" actual_end="2000.5.13 2.0" />
105       <task id="77" name="Choose legal representation" parent="70" progress="0%" actual_start="2000.5.12 17.0" actual_end="2000.5.13 2.0" />
106       <task id="78" name="Select business tax-basis category" parent="70" progress="0%" actual_start="2000.5.13 17.0" actual_end="2000.5.15 2.0" />
107       <task id="79" name="Choose capital funding source" parent="70" progress="0%" actual_start="2000.5.15 17.0" actual_end="2000.5.17 2.0" />
108       <task id="80" name="Commit capital funding" parent="70" progress="0%" actual_start="2000.5.17 2.0" actual_end="2000.5.17 2.0" />
109       <task id="81" name="Establish the Operating Control Base" parent="70" progress="19%" actual_start="2000.5.19 0.0" actual_end="2000.6.11 0.0" />
110       <task id="82" name="Choose and set up the accounting system" parent="81" progress="0%" actual_start="2000.5.19 17.0" actual_end="2000.5.21 2.0" />
111       <task id="83" name="Obtain required licenses and permits" parent="81" progress="38%" actual_start="2000.5.21 0.0" actual_end="2000.6.1 0.0" />
112       <task id="84" name="Obtain needed insurance" parent="81" progress="0%" actual_start="2000.6.3 17.0" actual_end="2000.6.7 2.0" />
113       <task id="85" name="Establish security plan" parent="81" progress="0%" actual_start="2000.6.7 17.0" actual_end="2000.6.11 2.0" />
114       <task id="86" name="Develop Marketing Program" parent="70" progress="0%" actual_start="2000.5.5 17.0" actual_end="2000.5.9 2.0" />
115       <task id="87" name="Establish an advertising program" parent="86" progress="0%" actual_start="2000.5.5 17.0" actual_end="2000.5.7 2.0" />
116       <task id="88" name="Develop a logo" parent="86" progress="0%" actual_start="2000.5.7 17.0" actual_end="2000.5.8 2.0" />
117       <task id="89" name="Order promotional materials" parent="86" progress="0%" actual_start="2000.5.8 17.0" actual_end="2000.5.9 2.0" />
118       <task id="90" name="Provide Physical Facilities" parent="68" progress="16%" actual_start="2000.6.11 0.0" actual_end="2000.7.24 0.0" />
119       <task id="91" name="Secure operation space" parent="90" progress="0%" actual_start="2000.6.11 17.0" actual_end="2000.6.18 2.0" />
120       <task id="92" name="Select computer network hardware" parent="90" progress="100%" actual_start="2000.6.18 17.0" actual_end="2000.6.19 2.0" />
121       <task id="93" name="Select computer software" parent="90" progress="0%" actual_start="2000.6.19 17.0" actual_end="2000.6.20 2.0" />
122       <task id="94" name="Establish utilities" parent="90" progress="67%" actual_start="2000.6.21 0.0" actual_end="2000.6.26 0.0" />
123       <task id="95" name="Provide furniture and equipment" parent="90" progress="15%" actual_start="2000.6.26 0.0" actual_end="2000.7.1 0.0" />
124       <task id="96" name="Move in" parent="90" progress="13%" actual_start="2000.7.23 0.0" actual_end="2000.7.24 0.0" />
125       <task id="97" name="Provide Staffing" parent="68" progress="30%" actual_start="2000.5.19 0.0" actual_end="2000.7.23 0.0" />
126       <task id="98" name="Interview and test candidates" parent="97" progress="43%" actual_start="2000.5.19 0.0" actual_end="2000.6.7 0.0" />
127       <task id="99" name="Hire staff" parent="97" progress="10%" actual_start="2000.6.7 0.0" actual_end="2000.6.21 0.0" />
128       <task id="100" name="Train staff" parent="97" progress="31%" actual_start="2000.7.1 0.0" actual_end="2000.7.23 0.0" />
129       <task id="102" name="Mau & Ago business" parent="97" progress="40%" actual_start="2000.1.24 0.0" actual_end="2000.2.2 0.0" />
130     </tasks>
131     <connectors>
132       <connector type="FinishStart" from="69" to="72" />
133       <connector type="FinishStart" from="46" to="49" />
134       <connector type="FinishStart" from="45" to="46" />
135       <connector type="FinishStart" from="25" to="28" />
136       <connector type="FinishStart" from="24" to="25" />
137       <connector type="FinishStart" from="99" to="100" />
138       <connector type="FinishStart" from="98" to="99" />
139       <connector type="FinishStart" from="95" to="96" />
140       <connector type="FinishStart" from="94" to="95" />
141       <connector type="FinishStart" from="93" to="94" />
142       <connector type="FinishStart" from="92" to="93" />
143       <connector type="FinishStart" from="91" to="92" />
144       <connector type="FinishStart" from="80" to="82" />
145       <connector type="FinishStart" from="79" to="80" />
146       <connector type="FinishStart" from="79" to="82" />
147       <connector type="FinishStart" from="79" to="98" />
148       <connector type="FinishStart" from="78" to="79" />
149       <connector type="FinishStart" from="77" to="78" />
150       <connector type="FinishStart" from="67" to="69" />
151       <connector type="FinishStart" from="66" to="67" />
152       <connector type="FinishStart" from="65" to="66" />
153       <connector type="FinishStart" from="64" to="65" />
154       <connector type="FinishStart" from="63" to="64" />
155       <connector type="FinishStart" from="62" to="63" />
156       <connector type="FinishStart" from="61" to="62" />
157       <connector type="FinishStart" from="60" to="61" />
158       <connector type="FinishStart" from="59" to="60" />
159       <connector type="FinishStart" from="58" to="59" />
160       <connector type="FinishStart" from="57" to="58" />
161       <connector type="FinishStart" from="56" to="57" />
162       <connector type="FinishStart" from="55" to="56" />
163       <connector type="FinishStart" from="54" to="55" />
164       <connector type="FinishStart" from="53" to="54" />
165       <connector type="FinishStart" from="52" to="53" />
166       <connector type="FinishStart" from="51" to="52" />
167       <connector type="FinishStart" from="50" to="51" />
168       <connector type="FinishStart" from="49" to="50" />
169       <connector type="FinishStart" from="44" to="45" />
170       <connector type="FinishStart" from="43" to="44" />
171       <connector type="FinishStart" from="42" to="43" />
172       <connector type="FinishStart" from="40" to="42" />
173       <connector type="FinishStart" from="39" to="40" />
174       <connector type="FinishStart" from="38" to="39" />
175       <connector type="FinishStart" from="37" to="38" />
176       <connector type="FinishStart" from="36" to="37" />
177       <connector type="FinishStart" from="35" to="36" />
178       <connector type="StartStart" from="33" to="35" />
179       <connector type="FinishStart" from="32" to="33" />
180       <connector type="FinishStart" from="31" to="32" />
181       <connector type="FinishStart" from="30" to="31" />
182       <connector type="FinishStart" from="28" to="29" />
183       <connector type="StartStart" from="28" to="35" />
184       <connector type="FinishStart" from="23" to="24" />
185       <connector type="FinishStart" from="22" to="23" />
186       <connector type="FinishStart" from="21" to="22" />
187       <connector type="FinishStart" from="19" to="20" />
188       <connector type="FinishStart" from="18" to="19" />
189       <connector type="FinishStart" from="17" to="18" />
190       <connector type="FinishStart" from="15" to="21" />
191       <connector type="FinishStart" from="14" to="15" />
192       <connector type="FinishStart" from="13" to="14" />
193       <connector type="FinishStart" from="12" to="13" />
194       <connector type="FinishStart" from="12" to="17" />
195       <connector type="FinishStart" from="10" to="12" />
196       <connector type="FinishStart" from="9" to="10" />
197       <connector type="FinishStart" from="8" to="9" />
198       <connector type="FinishStart" from="7" to="8" />
199       <connector type="FinishStart" from="5" to="7" />
200       <connector type="FinishStart" from="4" to="5" />
201       <connector type="FinishStart" from="3" to="4" />
202       <connector type="FinishStart" from="89" to="91" />
203       <connector type="FinishStart" from="88" to="89" />
204       <connector type="FinishStart" from="87" to="88" />
205       <connector type="FinishStart" from="85" to="91" />
206       <connector type="FinishStart" from="84" to="85" />
207       <connector type="FinishStart" from="83" to="84" />
208       <connector type="FinishStart" from="82" to="83" />
209       <connector type="StartStart" from="76" to="77" />
210       <connector type="FinishStart" from="75" to="76" />
211       <connector type="StartStart" from="75" to="77" />
212       <connector type="FinishStart" from="73" to="75" />
213       <connector type="StartStart" from="73" to="87" />
214       <connector type="FinishStart" from="72" to="73" />
215     </connectors>
216   </project_chart>
217 </anygantt>